Anchoring in deep water requires the Master and deck team to carefully assess the water depth, required anchor cable length, windlass capacity, and loads acting on the anchoring system. This article presents practical principles and calculations for deep water anchoring, together with key considerations during anchoring operations, anchoring large vessels, and anchor watch, with the aim of ensuring the safety of the vessel, equipment, and crew.
Deep water Anchoring
All vessels to walk back anchor under power to the desired scope in depths over 50meters. To avoid damaging the windlass, the anchor cable should be kept up/down and paid out continuously under power till the entire scope is paid out. When paying out the anchor chain, the speed over the ground should not be more than 0.3 knots. Engine and anchor brakes should be used as required to avoid over-speed and/or overload of the windlass motor.
Permissible water depth for anchoring is determined by the capacity of the windlass. Generally, the windlass has a lift capacity of 3 to 4 shackles with an anchor.
Sample calculation:
1. Cape size Bulker: Dead Weight: 181,412 MT / Windlass Capacity 382.4 kN
382.4 X 0.102 = 39 MT
Anchor weight: 12.075 MT
Chain weight: 1 shackle of 97mm diameter of common link: 0.206 t/m
0.206 X 27.5 M = 5.665 MT
4 shackles’ weight = 5.665 X 4 =22.66 MT
Total weight of an anchor and 4 SS of anchor chain
= 12.075 + 22.66 = 34.735 MT 4 SS X 27.5 = 110 meter.
Considering safety margin, friction on chain compressor, hawse pipe, anchor bell-mouth and additional chain weight from the windlass to the sea surface, the company policy of maximum permissible water depth for anchoring is 110m.Considering safety margin, friction on chain compressor, hawse pipe, anchor bell-mouth and additional chain weight from the windlass to the sea surface, the company policy of maximum permissible water depth for anchoring is 110m.
Regardless of the calculation mentioned above, some vessels are capable of lifting more than 4 shackles with an anchor (110m) based on their windlass capacity, however, a uniform policy on all managed vessels is considered to apply.
If the Master needs to anchor or is requested to do so at the depth more than permissible water depth, contacting the company is essential before anchoring.
Anchoring large vessels
On Anchoring /Anchor watch
You might be interested
The Night Order Book is an important tool for the Master to communicate specific instructions and safety precautions to the Officers of the Watch during the vessel’s night passage. The Night Order should be regularly updated to reflect the actual voyage conditions, weather, navigational area and operational status of the vessel, while remaining consistent with the Company’s SMS and relevant OCIMF/SIRE 2.0 practices. For LPG/LNG carriers, oil tankers and chemical tankers, particular attention should be given to navigational safety, CPA/TCPA, weather conditions, navigational equipment, cargo operations and other vessel-specific risks. For LPG/LNG carriers, additional considerations may include cargo tank pressure and temperature, the reliquefaction plant, gas detection systems and cargo tank conditions.
See moreAs part of its ongoing commitment to improving the professional competence of Vietnamese seafarers, SUNRISE MANPOWER CO., LTD successfully organized a Specialized 4th Engineer Training Session. The training focused not only on strengthening technical knowledge but also on providing participants with opportunities to work directly with equipment, discuss real-life operational situations, and learn practical experience from experienced Chief Engineers. This training program is one of SUNRISE MANPOWER’s practical initiatives to support seafarers in enhancing their skills, becoming more confident in their duties, and maintaining safe operations on board.
See moreProtective Shields are additional safety devices fitted around the cylinder ends of some MAN B&W ME engines, particularly at Cylinder No. 1 and No. 6. Although they are not standard factory equipment, many shipowners require their installation to protect crew members from high-temperature combustion gases that may escape under abnormal cylinder pressure, especially during main engine starting. The article explains the reason for their installation and why the arrangement may differ between engines of the same type.
See more